Numerical Simulation Study on Residual Blasthole Length of Auxiliary Holes in Hard Rock Tunnel Blasting
YUAN Yue-ming;XU Bang-shu;LIU Hong;CAI Hui;FAN Fei-fei;LIU Hong-liang;GAO Lei;WANG Zhuo-xuan;
Abstract:
In tunnel blasting operations,the performance of auxiliary holes following initial cut blasting critically influences subsequent excavation progress and operational efficiency. The residual borehole length after auxiliary-hole detonation is a crucial parameter for assessing both the efficiency of blasting energy utilization and the effectiveness of rock fragmentation. This study investigates the impact of the residual borehole length after auxiliary-hole blasting in hard-rock tunnels on subsequent excavation performance,using the Fangshan Tunnel as a case study. A three-dimensional dual-borehole model was developed in Hypermesh with localized mesh refinement around blast holes. LS-DYNA simulations were conducted to analyze residual hole lengths under varying inter-hole delay times and geological conditions,with key parameters systematically configured for blast dynamics analysis. This research systematically examines the governing patterns of inter-hole delay time and surrounding rock mass on the residual borehole length in auxiliary holes,employing advanced numerical simulation techniques for comprehensive parametric analysis. The results demonstrate that the inter-hole delay time significantly influences residual borehole length,with longer delay times within a specific range increasing residual length and accelerating growth rate. Furthermore,the lithology of the surrounding rock mass emerges as a critical determinant of residual length,with granite exhibiting longer residual holes than sandstone under identical charging conditions,revealing a positive correlation between the rock firmness coefficient and residual hole dimensions. Field verification was conducted using optimized auxiliary hole blasting parameters derived from this study. The implementation of these parameters in actual construction effectively controlled the residual borehole length and significantly enhanced blasting performance in hard-rock tunnel excavation. The findings establish both theoretical foundations and methodologies for precision design and dynamic adjustment of auxiliary hole blasting parameters in hard rock tunnel excavation,offering substantial value for enhancing construction efficiency and optimizing project economics in tunneling operations.
Key Words: numerical simulation;hard rock tunnel;tunnel blasting;auxiliary hole;residual hole
Foundation: 国家自然科学基金(52379102)深埋隧道开挖扰动围岩能量释放特征与吸能支护结构协同作用机理;国家自然科学基金(50909056)海底隧道覆盖岩层失稳机理及最小岩石覆盖厚度分析方法研究;; 山东省自然科学基金(ZR2021QE246)层状岩体隧道爆破开挖围岩成型机理及爆破参数智能优化方法~~
Authors: YUAN Yue-ming;XU Bang-shu;LIU Hong;CAI Hui;FAN Fei-fei;LIU Hong-liang;GAO Lei;WANG Zhuo-xuan;
References:
- [1]马乐,张万志,刘成龙,等.Ⅲ级硬岩隧道全断面光面爆破试验研究[J].爆破,2023,40(3):46-51,67.[1]MA Le,ZHANG Wang-zhi,LIU Cheng-long,et al. Experimental study on full face smooth blasting of tunnel in classⅢ hard rock[J]. Blasting,2023,40(3):46-51,67.(in Chinese)
- [2]夏星.隧道爆破掏槽孔及辅助孔起爆时差优化研究[D].武汉:江汉大学,2024.[2]XIA Xing. Tunnel blasting hollowing hole and auxiliary hole detonation time difference study[D]. Wuhan:Jianghan Uniyersity,2024.(in Chinese)
- [3]李洪伟,吴延梦,吴立辉,等.电子雷管起爆条件下隧道掏槽孔与辅助孔的延时优化试验研究[J].高压物理学报,2023,37(1):171-181.[3]LI Hong-wei,WU Yan-meng,WU Li-hui,et al. Experimental study on delay optimization of trench cutting holes and auxiliary holes under electronic detonator initiation conditions[J]. Chinese Journal of High Pressure Physics,2023,37(1):171-181.(in Chinese)
- [4]CHEN Ying-xian,WANG Peng-fei,CHEN Jian,et al. Calculation of blast hole charge amount based on three-dimensional solid model of blasting rock mass[J]. Scientific Reports,2022,12(1):541-541.
- [5]MA Xin-min,CHEN Zhen-yu,CHEN Pan,et al. Predicting the utilization factor of blasthole in rock roadways by random forest[J]. Underground Space,2023,11:232-245.
- [6]李萍丰,王秀龙,闫小兵,等.柱状药包侧向爆破下抵抗线对岩石破碎特性的影响研究[J].岩土力学,2024,45(5):1388-1396.[6]LI Ping-feng,WANG Xiu-long,YAN Xiao-bing,et al.Effects of burden on rock crushing characteristics under lateral detonation of cylindrical charges[J]. Rock and Soil Mechanics,2024,45(5):1388-1396.(in Chinese)
- [7]WU Xiao-dong,JIA Jia-yin,WANG Li-kun,et al. Easer hole design method based on the principle of minimum burden at the hole bottom and its application in tunnel blasting[J]. Processes,2024,12(8):1581-1581.
- [8]YU Bing-bing,WANG Bo,LI Yi,et al. Prediction of blasthole utilization rate using structured nonlinear support vector machine combined with optimization algorithms[J]. Applied Intelligence,2024,54(19):9136-9157.
- [9]徐帮树,杜念伟,王帅帅,等.马蹄形隧道拱脚周边孔爆破围岩的损伤特征[J].爆炸与冲击,2025,45(8):177-189.[9]XU Bang-shu,DU Nian-wei,WANG Shuai-shuai,et al.Blasting damage characteristics of surrounding rock around the arch foot of horseshoe tunnel[J]. Explosion and Shock Waves,2025,45(8):177-189.(in Chinese)
- [10]李洪超,王富旗,张继,等.岩石RHT模型部分参数的敏感性分析及确定[J].高压物理学报,2025,39(6):66-76.[10]LI Hong-chao,WANG Fu-qi,ZHANG Ji,et al. Sensitivity analysis and determination of some parameters of the RHT rock model[J]. Chinese Journal of High Pressure Physics,2025,39(6):66-76.(in Chinese)
- [11]彭正阳,黄震,秦茂豇,等.内部与地表爆炸作用下装配式框架隧道结构动力响应及抗爆性能[J].隧道建设(中英文),2025,45(11):2140-2154.[11]PENG Zheng-yang,HUANG Zhen,QIN Mao-jiang,et al.Dynamic response and blast resistance performance of assembled frame tunnel structures under internal and surface explosion effects[J]. Tunnel Construction,2025,45(11):2140-2154.(in Chinese)
- [12]XIE Li-xiang,LU Wen-bo,ZHANG Qian-bing,et al. Analysis of damage mechanisms and optimization of cut blasting design under high in-situ stresses[J]. Tunnelling and Underground Space Technology,2017,66:19-33.
- [13]刘翔宇,龚敏,杨仁树,等.隧道周边孔毫秒延时爆破围岩损伤数值分析研究[J].振动与冲击,2023,42(24):8-15.[13]LIU Xiang-yu,GONG Min,YANG Ren-shu,et al. Numerical analysis of surrounding rock damage caused by millisecond delay blasting of tunnel peripheral holes[J].Journal of Vibration and Shock,2023,42(24):8-15.(in Chinese)
- [14]KAMRAN M,LIU Hong-yuan,FUKUDA D,et al. Stateof-the-art review and prospect of modelling the dynamic fracture of rocks under impact loads and application in blasting[J]. Geosciences,2025,15(8):314.
- [15]阚吉亮,窦林名,周坤友,等.多孔爆破岩石破坏机制及起爆方式选择[J].采矿与安全工程学报,2025,42(5):1175-1187.[15]KAN Ji-liang,DOU Lin-ming,ZHOU Kun-you,et al.Rock failure mechanism of multi-hole blasting and selection of initiation pattern[J]. Journal of Mining&Safety Engineering,2025,42(5):1175-1187.
- YUAN Yue-ming
- XU Bang-shu
- LIU Hong
- CAI Hui
- FAN Fei-fei
- LIU Hong-liang
- GAO Lei
- WANG Zhuo-xuan
- Shandong High-Speed Construction Management Group Co.
- LTD.
- School of Qilu Transportation
- Shandong University
- Linteng Highway Co.
- Ltd.of Shandong High-Speed
- YUAN Yue-ming
- XU Bang-shu
- LIU Hong
- CAI Hui
- FAN Fei-fei
- LIU Hong-liang
- GAO Lei
- WANG Zhuo-xuan
- Shandong High-Speed Construction Management Group Co.
- LTD.
- School of Qilu Transportation
- Shandong University
- Linteng Highway Co.
- Ltd.of Shandong High-Speed